North Corridor Highway & Interchange
redHW-11 · Roads & Infrastructure · Remeasured · Riyadh, KSA
Client: National Roads Authority · Consultant: Vertex Infra Consultants · PM: Layla Kassem · 2023-09-15 → 2026-03-31
Contract
$214M
Approved VOs
$11.8M
CPI
0.95
SPI
0.87
Warning: a superseded drawing revision exists in this project register. Site teams must use the latest approved revision only.
Budget
$189M
Committed
$158.4M
83.8% of budget
Actual cost
$141.7M
Forecast (EAC)
$201.3M
Overrun forecast
Invoiced
$149M
Collected
$121.4M
Receivables
$27.6M
Physical progress
71%
Planned 82%