OH
BuildFlow/Projects/HW-11

North Corridor Highway & Interchange

red

HW-11 · Roads & Infrastructure · Remeasured · Riyadh, KSA

Client: National Roads Authority · Consultant: Vertex Infra Consultants · PM: Layla Kassem · 2023-09-15 2026-03-31

Contract

$214M

Approved VOs

$11.8M

CPI

0.95

SPI

0.87

Warning: a superseded drawing revision exists in this project register. Site teams must use the latest approved revision only.

Budget

$189M

Committed

$158.4M

83.8% of budget

Actual cost

$141.7M

Forecast (EAC)

$201.3M

Overrun forecast

Invoiced

$149M

Collected

$121.4M

Receivables

$27.6M

Physical progress

71%

Planned 82%

S-curve: planned vs actual progress